Switchboard upgrade — Tuas factory

Replaced an ageing main switchboard and three sub-DBs for a 24/7 manufacturing line — without stopping production.

Industrial Tuas, Singapore 6 weeks
Switchboard upgrade — Tuas factory
Sector
Industrial
Capacity
1600 A
Downtime
0 hrs
Duration
6 wks
The brief

What the client needed.

The existing 1990s switchboard was tripping under modern loads, and the tenant could not shut the line for more than a 4-hour overnight window. Cable runs had to be relocated around active machinery and an overhead crane track.

Our approach

How we delivered it.

We pre-built the new switchboard off-site, staged a temporary bypass feed, and cut-over in two scheduled 3-hour outages. EMA-licensed workers handled all live terminations; we coordinated with the tenant's safety officer for daily permits.

Outcome

The result on hand-over.

Zero unplanned downtime. New board commissioned with full load test report, single-line diagrams updated, and a 12-month workmanship warranty issued on hand-over.

Scope delivered

What we installed.

  • Form-4 main switchboard, 1600A
  • Three sub-distribution boards
  • Load testing & thermographic scan
  • Updated single-line drawings
  • EMA sign-off documentation