05Case study · 2025

Reinstatement — CBD office

Stripped an 18,000 sq ft CBD floor back to bare-shell condition for landlord hand-over, covering electrical, ACMV, partitions and finishes.

Commercial Raffles Place, Singapore 5 weeks
Reinstatement — CBD office
Sector
Commercial
Area
18k ft²
Trades
6
Finish
−4 days
The brief

What the client needed.

Hard deadline — penalty rent on overshoot. Building had restrictive after-hours hot-works rules and a single goods lift shared with active tenants.

Our approach

How we delivered it.

Ran six trades in parallel on a tight programme. Pre-booked all lift slots, used cold-cut methods to avoid hot-work permits, and stationed a full-time site supervisor.

Outcome

The result on hand-over.

Handed over four days ahead of schedule. Landlord signed off on the first walk-through.

Scope delivered

What we installed.

  • Electrical & ACMV strip-out
  • Partition + ceiling removal
  • Floor screed repair, repaint
  • Waste disposal manifests
  • Landlord hand-over pack